A load break switch, or a disconnector or disconnect switch, can serve as enclosures for overcurrent protection and ground fault protection. Ensure that the switches are maintained and are functioning properly by performing visual inspections and mechanical testings using this form. Check that the switches are in their required operating position, that they are free of chips or cracks, and inspect the linkages and operating handles for signs of damage. Take photos of any visual defects and use the inspection results to inform corrective measures as necessary. This form is customizable to suit your inspection requirements and maintenance guidelines and works in both on and offline environments.

Load Break Disconnect Switch Inspection Checklist iPhone, iPad Load Break Disconnect Switch Inspection Checklist Android Load Break Disconnect Switch Inspection Checklist Web, Desktop
Load Break Disconnect Switch Inspection Checklist

General

Location

Inspection Date

Disconnect Switch Serial Number

Type/Model

Manufacturer

Year

Operating Position

Voltage/Current Rating

Mechanism Type

Test/Measurements

Contact Resistance

Thermovision Reading

Auxiliary Volts

Ambient Temperature

Checklist Items

Manual Operation

Observations/readings

Date Corrected

Porcelain Condition

Observations/readings

Date Corrected

Contact

Observations/readings

Date Corrected

Lubricate Contacts

Observations/readings

Date Corrected

Hinge End Shunt

Observations/readings

Date Corrected

Lubricate linkeages

Observations/readings

Date Corrected

Gear Box

Observations/readings

Date Corrected

Connections

Observations/readings

Date Corrected

Insulator Stacks

Observations/readings

Date Corrected

Clean and paint corroded linkages and mechanisms

Observations/readings

Date Corrected

Test operate disconnect switch

Observations/readings

Date Corrected

Contact Resistance

Observations/readings

Date Corrected

Connection to Connection Phase A

Observations/readings

Date Corrected

Connection to Connection Phase B

Observations/readings

Date Corrected

Connection to Connection Phase C

Observations/readings

Date Corrected

Motor Mechanism Inspection

Observations/readings

Date Corrected

Mechanism Cabinet

Observations/readings

Date Corrected

Anti Condensation

Observations/readings

Date Corrected

Auxiliary Switches

Observations/readings

Date Corrected

Lubricate Operating Mechanism

Observations/readings

Date Corrected

Interlock switches & locking devices

Observations/readings

Date Corrected

Photos

Signature